
Reviewing a BIFA adjudication decision is an option for a party
who believes that there has been jurisdictional error, including a
lack of procedural fairness in the adjudication decision.
The Supreme Court of Queensland has a supervisory jurisdiction
to review an adjudicator’s decision under the Queensland Building Industry Fairness (Security of
Payments) Act 2017 (Qld)
(“BIFA“).
The only way that a BIFA adjudication decision can be reviewed
is on grounds of jurisdictional error.
There are many ways that jurisdictional error can arise, and
some common examples are where the adjudicator:
- fails to do something they are required to do – such as
consider a document required by legislation to be considered, or
give a party an opportunity to express their position; - does something they are not allowed to do – such as consider a
document they are prohibited by legislation from considering or
deny a party an opportunity to express their position; or - proceeds as if they have jurisdiction, but in fact the
jurisdictional “threshold” requirements have not been
met.
It is impossible to identify all the potential jurisdictional
errors, but this article sets out some of the issues which commonly
arise.
This article on reviewing a BIFA adjudication decision is
co-written by our building and constructions lawyers and
Merissa Martinez of
Counsel, building and construction barrister from
Paloma Chambers in Townsville.
The Purpose of BIFA
The main purpose of BIFA is to help people who work in the
building and construction industry to get paid. Cash is the life
blood of the industry, and therefore it must be kept flowing.
BIFA provides a procedure for sending invoices (payment claims)
with strict time limits and content requirements; and responding to
payment claims (payment schedules) within strict time limits and
content requirements to enable the payee to better understand how
much, and when, they will get paid.
BIFA also has a mechanism for the adjudication of disputed
payment claims and the recovery of money claimed by the payee. This
is a quick and cost-effective resolution to building and
construction payment disputes.
Whilst it does not have a costs jurisdiction per se, the
adjudicator will decide, as part of their decision, who pays the
adjudicator’s fees.
The fast-track resolution means that not every mistake of fact
or law will amount to jurisdictional error. Put simply, there are
certain errors which are within an adjudicator’s jurisdiction
to make.
Errors which do not go to jurisdiction are “precisely
the kind of departure from contractual and legal precision which
the legislature has accepted as part of the ‘trade-off’ for
speed and efficiency”: Laing O’Rourke Australia Construction Pty
Ltd v Samsung C&T Corporation [2016] WASCA 130, per
Martin CJ at [107].
BIFA does a lot of other things in relation to payment, but the
scope of this article is limited to identifying the line between
errors within jurisdiction to make, and errors which amount to
jurisdictional error.
This line is sometimes difficult to discern. Set out below are
some examples of both jurisdictional errors and non-jurisdictional
errors.
Jurisdiction to Adjudicate the Application
Section 84(2)(a)(i) of BIFA requires the adjudicator
to decide whether they have jurisdiction to adjudicate the
adjudication application.
Even if the respondent does not make any jurisdictional
challenges about the applicant’s entitlement to make the
payment claim and adjudication application, the adjudicator must
nonetheless be satisfied that BIFA applies in order to proceed
further.
An adjudicator has jurisdiction if:
- there is a “construction contract” to which BIFA
applies; - there is an entitlement to make a payment claim with a
“reference date”; - a valid “payment claim” has been properly served on
the payer at the right time; - an adjudication application has been made to the registrar in
the approved form within the correct time period; - the application had been referred to, and accepted by, an
eligible adjudicator within the correct time period; and - the adjudicator determines the claim strictly in accordance
with their powers.
Each of these jurisdictional issues that can be used when
reviewing a BIFA adjudication decision are expanded on briefly
below.
Existence of a Construction Contract
A construction contract (whether written or oral, or partly
written and partly oral) is defined as:
a contract, agreement or other arrangement under which 1
party undertakes to carry out construction work for, or to supply
related goods and services to, another party.
The standard questions of formation of contract arise, but in
this industry, there can sometimes be questions of whether the
contract is an excluded contract or does not in fact cover
“construction work” as that expression is defined.
Section 65 of BIFA defines construction work.
It is an extensive list which includes (but is not limited to) the
following:
the construction, alteration, repair, restoration,
maintenance, extension, demolition or dismantling of buildings or
structures, whether permanent or not, forming, or to form, part of
land;
the construction, alteration, repair, restoration,
maintenance, extension, demolition or dismantling of any works
forming, or to form, part of land, including walls, roadworks,
powerlines, telecommunication apparatus, aircraft runways, docks
and harbours, railways, inland waterways, pipelines, reservoirs,
water mains, wells, sewers, industrial plant and installations for
land drainage or coast protection;
the installation in any building, structure or works of
fittings forming, or to form, part of land, including heating,
lighting, air-conditioning, ventilation, power supply, drainage,
sanitation, water supply, fire protection, security and
communications systems.
Section 65(3) expressly excludes certain
work:
However, “construction work” does not include any
of the following work-
(a) the drilling for, or extraction of, oil or natural
gas;
(b) the extraction, whether by underground or surface
working, of minerals, including tunnelling or boring, or
constructing underground works, for that purpose.
There are also relevant provisions in the Regulations. As BIFA
only applies to construction contracts, the statutory right to
payment and adjudication are predicated upon the relevant works
being caught by the statutory definition. So this is the first
consideration when reviewing a BIFA adjudication decision.
Entitlement to Make a Payment Claim
In relation to the entitlement to make a payment claim, section 70 of BIFA says:
From each reference date under a construction contract, a
person is entitled to a progress payment if the person has carried
out construction work, or supplied related goods and services,
under the contract.
Whether a reference date arises is a matter to be determined
under the contract and within the legislative framework of
BIFA.
Section 67 of BIFA gives us a definition of
“reference date”. It says:
(1) A “reference date” , for a construction
contract, means-
(a) a date stated in, or worked out under, the contract as
the date on which a claim for a progress payment may be made for
construction work carried out, or related goods and services
supplied, under the contract; or
(b) if the contract does not provide for the
matter-
(i) the last day of the month in which the construction work
was first carried out, or the related goods and services were first
supplied, under the contract; and
(ii) the last day of each later month.
(2) However, if a construction contract is terminated and
the contract does not provide for, or purports to prevent, a
reference date surviving beyond termination, the final reference
date for the contract is the date the contract is
terminated.
Without a reference date, there is no statutory right to
payment. Therefore, careful analysis of the statutory regime, the
contractual regime and the factual matrix is important to ascertain
if a reference date has arisen.
If not, then this can be another reason for reviewing a BIFA
adjudication decision.
Service of a Payment Claim
In relation to service, section 102 of BIFA says that a notice or
other document under this chapter can be served pursuant to a term
or terms in the construction contract; or pursuant to section 39 of the Acts Interpretation Act 1954
(QLD) which says:
If an Act requires or permits a document to be served on a
person, the document may be served-
On an individual-by delivering it to the person personally;
or by leaving it at, or by sending it by post, telex, facsimile or
similar facility to, the address of the place of residence or
business of the person last known to the person serving the
document; or
On a body corporate-by leaving it at, or sending it by post,
telex, facsimile or similar facility to, the head office, a
registered office or a principal office of the body
corporate.
There are also temporal requirements in relation to serving
payment claims.
Section 75(2) of BIFA states that a payment
claim must be given in the period worked out under the construction
contract or 6 months after the construction work to was last
carried out:
(2) Unless the payment claim relates to a final payment, the
claim must be given before the end of whichever of the following
periods is the longest-
(a) the period, if any, worked out under the construction
contract;
(b) the period of 6 months after the construction work to
which the claim relates was last carried out or the related goods
and services to which the claim relates were last
supplied.
If the payment claim is a final payment claim, then section
75(3) of BIFA states that the claim must be given before the end of
whichever of the following periods is the longest:
(a) the period, if any, worked out under the relevant
construction contract;
(b) 28 days after the end of the last defects liability
period for the construction contract;
(c) 6 months after the completion of all construction work
to be carried out under the construction contract;
(d) 6 months after the complete supply of related goods and
services to be supplied under the construction contract.
For more on payment claims read our article on making BIFA payment
claims.
It is important to ascertain as a matter of fact when the last
construction work was carried out, or when the goods and services
were last supplied – this will permit the clock to start ticking.
If not, then this may allow the review of a BIFA adjudication
decision.
Adjudication Application made to Registrar in the Approved
Form
The Registrar is the Queensland Building and construction Commission
(“QBCC“).
The approved form for the QBCC adjudication application in
Queensland is QBCC Form S79 Adjudication Application.
The application is made if it is delivered in person to a QBCC
regional office or posting it to the QBCC. There are strict time
limits.
Section 79(2)(b) of BIFA says that an
application must be made within:
For an application relating to a failure to give a payment
schedule and pay the full amount stated in the payment
claim-30 business days after the later of the
following days:
* the day of the due date for the progress payment to which
the claim relates;
* the last day the respondent could have given the payment
schedule under section 76; or
For an application relating to a failure to pay the full
amount stated in the payment schedule – 20 business
days after the due date for the progress payment to which
the claim relates; or
For an application relating to the amount stated in the
payment schedule being less than the amount stated in the payment
claim – 30 business days after the claimant receives the payment
schedule.
So, a claimant has either 20 or 30 business days to make an
application for adjudication depending on the particular
circumstances of your dispute. These are guillotine deadlines with
which applicants must comply.
Adjudication Application Referred and Accepted by an Eligible
Adjudicator
A list of adjudicators is kept by the QBCC – https://www.qbcc.qld.gov.au/about-us/adjudication-registry
The adjudicator must be a registered and licensed
adjudicator.
For more on making adjudication applications read our article -
How to Make an Adjudication
Application.
Valid Determination by the Adjudicator
Section 88 of BIFA outlines how the adjudicator must decide the
adjudication application. Section 88 of BIFA includes directions in
relation to:
- What the adjudicator must decide;
- What the adjudicator must consider;
- What the adjudicator must not consider; and
- The form and procedure of the adjudication decision.
The relevant provisions of BIFA for each of these are identified
below.
What the Adjudicator must Decide
Section 88(1) of BIFA states:
(1) An adjudicator is to decide-
(a) the amount of the progress payment, if any, to be paid
by the respondent to the claimant (the “adjudicated
amount”); and
(b) the date on which any amount became or becomes payable;
and
(c) the rate of interest payable on any amount.
This section operates in two ways: first, it identifies what
must be determined, and a decision which does not fulfil the
requirements is not a valid decision.
Second, it identifies the extent of the adjudicator’s
jurisdiction, so that if the adjudicator steps outside of these
limits, the decision will be ultra vires.
What the Adjudicator must Consider
Section 88(2) of BIFA states:
(2) In deciding an adjudication application, the adjudicator
is to consider the following matters
only–
(a) the provisions of this chapter and, to the extent they
are relevant, the provisions of the Queensland Building and
Construction Commission Act 1991 , part 4A ;
(b) the provisions of the relevant construction
contract;
(c) the payment claim to which the application relates,
together with all submissions, including relevant documents, that
have been properly made by the claimant in support of the
claim;
(d) the payment schedule, if any, to which the application
relates, together with all submissions, including relevant
documents, that have been properly made by the respondent in
support of the schedule;
(e) the results of any inspection carried out by the
adjudicator of any matter to which the claim relates.
Therefore if an adjudicator considers something outside of this
in reaching their decision, this may be grounds for challenging the
enforceability.
What the Adjudicator must not Consider
Section 88(3) of BIFA states:
(3) However, the adjudicator must not consider any of the
following-
(a) an adjudication response, to which the adjudication
application relates, that was not given to the adjudicator within
the time required under section 83 ;
(b) a reason included in an adjudication response to the
adjudication application, if the reason is prohibited from being
included in the response under section 82.
Section 88(4) of BIFA states:
(4) Also, the adjudicator may disregard an adjudication
application or adjudication response to the extent that the
submissions or accompanying documents contravene any limitations
relating to submissions or accompanying documents prescribed by
regulation.
The importance of these decisions by an adjudicator about what
they are entitled to consider and not entitled to consider are
discussed in greater detail below.
The Form and Procedure of the Adjudication Decision
Section 88(5) of BIFA states:
(5) The adjudicator’s decision must-
(a) be in writing; and
(b) include the reasons for the decision, unless the
claimant and the respondent have both asked the adjudicator not to
include the reasons in the decision.
Section 88(6) of BIFA states:
(6) The adjudicator must give the registrar-
(a) a copy of the decision; and
(b) notice of all fees and expenses paid, and to be paid, to
the adjudicator for the decision.
Section 88(6) of BIFA states:
(7) The adjudicator must give the registrar the information
mentioned in subsection (6) at the same time the adjudicator gives
a copy of the decision to the claimant and the respondent.
Whilst the technical compliance with the decision being in
writing and submitted appropriately is obvious, this section does
raise issues about the adequacy of the reasons provided, as
discussed further below.
Jurisdiction of the Supreme Court
An adjudicator’s decision under BIFA is an administrative
decision over which the Supreme Court of Queensland has a supervisory
jurisdiction to review a BIFA adjudication decision.
In Brodyn Pty Ltd t/as Time Cost and Quality v
Davenport & Anor [2004] NSWCA 394, Hodgson JA with
Mason P and Giles JA agreeing, looked at the line of authorities
and said at [44]:
It was decided in Musico v. Davenport [2003] NSWSC 977 that
relief in the nature of certiorari is available against an
adjudicator’s determination, albeit not on the ground of
non-jurisdictional error of law on the face of the record. This has
been followed in a number of other first instance decisions,
including Abacus Funds Management v. Davenport [2003] NSWSC 1027,
Brodyn Pty. Limited v. Davenport [2003] NSWSC 1019, Multiplex
Constructions Pty. Limited v. Luikens [2003] NSWSC 1140 and
Transgrid v. Walter Construction Group [2004] NSWSC 21.
The Court has inherent jurisdiction to grant declaratory and
injunctive relief in relation to adjudicators’ determinations
under BIFA.
Adjudications which do not comply with the essential statutory
requirements are void and the Court may, when non-compliance has
been demonstrated, make declarations and/or grant injunctions to
prevent a party acting on a void adjudication.
What is Jurisdictional Error?
The main reason for reviewing a BIFA adjudication decision is
because of jurisdictional error.
The High
Court of Australia in Kirk v Industrial Relations Commission [2010]
HCA 1 confirmed that jurisdictional error may arise due to
“the absence of a jurisdictional fact”. The Court said at
[72]:
The Court amplified what was said about an inferior court
acting beyond jurisdiction by entertaining a matter outside the
limits of the inferior court’s functions or powers by giving
three examples:
(a) the absence of a jurisdictional fact;
(b) disregard of a matter that the relevant statute requires
be taken to account as a condition of jurisdiction (or the converse
case of taking account of a matter required to be ignored);
and
(c) misconstruction of the relevant statute thereby
misconceiving the nature of the function which the inferior court
is performing or the extent of its powers in the circumstances of
the particular case.
In Chase Oyster Bar v Hamo Industries [2010]
NSWCA 190, McDougall J referred to Kirk v Industrial Court
of New South Wales and said at [158]:
The majority pointed out at 573[71] that “[i]t is
neither necessary, nor possible, to attempt to mark the metes and
bounds of jurisdictional error”. However, by reference
to the decision in Craig v South Australia [1995] HCA
58; (1995) 184 CLR 163, 177-178, the majority identified three
categories of jurisdictional error (Kirk at 573-574[72]):
(1) the mistaken denial or assertion of jurisdiction, or (in
a case where jurisdiction does exist), misapprehension or disregard
of the nature of or limits on functions and powers;
(2) entertaining a matter or making a decision of a kind
that lies, wholly or partly, outside the limits on functions and
powers, as identified from the relevant statutory context;
(3) proceeding in the absence of a jurisdictional fact;
disregarding something that the relevant statute requires to be
considered as a condition of jurisdiction or considering something
required to be ignored; and misconstruction of the statute leading
to misconception of functions. (Of this last example, it was said
in Craig at 178 that “the line between jurisdictional error
and mere error in the exercise of jurisdiction may be particularly
difficult to discern.”)
In accordance with the purpose of BIFA, even if an adjudicator
has made an obvious mistake (including error of law or fact), as
long as the adjudicator had the power to make the mistake, the
courts will not likely disturb the adjudicated decision.
In Brodyn Pty Ltd (t/as Time Cost & Quality)
v Davenport (2004) 61 NSWLR 421; and Transgrid v Siemens Ltd (2004) 61 NSWLR
521, Hodgson JA with Mason P and Giles JA agreeing, said that
judicial review will be allowed in the following circumstances:
- The adjudicator failed to comply with the requirements of
[BIFA] for valid determination; - The adjudicator denied natural justice to one (or both) of the
parties; and/or - The adjudication was fraudulent (with complicity of the
adjudicator).
Examples of jurisdictional error can arise across an indefinable
gambit, including where the adjudication decision:
- was given by fraud or in bad faith;
- was made where there is a reasonable apprehension of bias
- was made without complying with the statutorily imposed short
time frames; - was one which the adjudicator had no power to make due to the
lack of a jurisdictional fact; - was reached by the adjudicator determining a question which was
not submitted for adjudication; - did not deal with the question submitted for adjudication;
and/or - was reached by the adjudicator failing, neglecting, or refusing
to take into account something which the Act required.
What do the Cases Say about Jurisdictional Error?
To assist the reader in understanding if jurisdictional error
applies to their matter, and therefore capable of judicial review,
several common examples of jurisdictional error are discussed
below.
The Threshold Issues must be Met
The first thing to consider is whether all of the threshold
issues have been adequately or correctly considered in the
adjudication decision. Set out above are some of the threshold
issues, which can commonly include:
- Was/is there a relevant construction contract to which the Act
applies; - Was/is the builder licensed to do the works the subject of the
Contract; - Was the payment claim properly made by the applicant, and
within the requisite time; - Was a payment schedule properly made by the respondent, and
within the requisite time; - Was the adjudication application properly made by the
applicant, and within the requisite time; and - Was the adjudication response properly made by the respondent,
and within the requisite time.
If these things have not been done correctly, then the
adjudicator may not have grounds to make the adjudication
application.
The adjudicator must fulfil their statutory function.
The Adjudicator Must Fulfil their Statutory Function
As above, section 88 of BIFA states what the statutory
functions of the adjudicator are. The statutory functions are the
adjudicator are:
- To decide the amount of the progress payment, if any, to be
paid by the respondent to the claimant. - To decide the date on which any amount became or becomes
payable. - To decide the rate of interest payable on any amount.
- To consider the provisions of this chapter and, to the extent
they are relevant, the provisions of the Queensland Building
and Construction Commission Act 1991, part 4A. - To consider the provisions of the relevant construction
contract. - To consider the payment claim to which the application relates,
together with all submissions, including relevant documents, that
have been properly made by the claimant. - To consider the payment schedule, if any, to which the
application relates, together with all submissions, including
relevant documents, that have been properly made by the
respondent. - To consider the results of any inspection carried out by the
adjudicator of any matter to which the claim relates. - To not consider an adjudication response that was not given to
the adjudicator within the time required under section 83. - To not consider a reason included in an adjudication response
to the adjudication application, if the reason is prohibited from
being included in the response under section 82. - To disregard an adjudication application or adjudication
response to the extent that the submissions or accompanying
documents contravene any limitations relating to submissions or
accompanying documents prescribed by regulation. - To provide the adjudication decision in writing.
- To include the reasons for the adjudication decision.
- To give the registrar a copy of the decision at the same time
the adjudicator gives a copy of the decision to the claimant and
the respondent. - To give the registrar notice of all fees and expenses paid, and
to be paid, to the adjudicator for the decision at the same time
the adjudicator gives a copy of the decision to the claimant and
the respondent.
New Reasons in Adjudication Response
Section 88(3)(b) of the BIFA says:
(3) However, the adjudicator must not consider any of the
following –
. (b) a reason included in an adjudication response to the
adjudication application if the reason is prohibited from being
included in the response under section 82.
Section 82(4) of the BIFA says:
However, the adjudication response must not include any
reasons (new reasons) for withholding payment that were not
included in the payment schedule when given to the
claimant.
There are two types of decisions which can arise in relation to
“new reasons”. The first is where an adjudicator
erroneously makes a decision to consider reasons which were in fact
“new reasons”. The second is where an adjudicator makes a
decision that reasons are “new reasons” and refuses to
consider them. The former is reviewable, the latter is not.
In Acciona Agua Australia Pty Ltd v Monadelphous
Engineering Pty Ltd [2020] QSC 133
(Acciona) the Court considered
whether the respondent’s reasons were “new reasons”
not raised in the payment schedule and whether the adjudicator, in
improperly considering these reasons, fell into jurisdictional
error.
His Honour Justice Bond concluded that the adjudicator’s
acceptance of the “new reasons” in the
adjudication response treated the distinction between a reason in
the payment schedule and a “new reason” in an
adjudication response “in such a way as would undermine
the policy underlying the introduction of the new provisions in ss
82 and 88“, thereby denying the claimant the opportunity
to engage with those submissions in its adjudication
application.
There, the adjudicator’s decision was attended by
jurisdictional error because he had improperly considered a
“new reason” and accordingly, the adjudicator failed to
comply with the condition in section 88(3)(b).
However, Acciona is fundamentally different (both
conceptually and in the line of some of the authorities addressing
it) from a decision by an adjudicator who has decided to exclude
consideration under section 88(2)(d) of adjudication submissions
on the basis they were not “properly made” or prohibited
by operation of section 82(4) or section 88(3)(b).
In Acciona, Justice Bond referred to John Holland Pty Ltd v Roads & Traffic
Authority of New South Wales [2007] NSWCA 19 at [54],[55]
and [71]; Acciona per Justice Bond at [36(c) and (d)]:
“the settled law” that “a mere failure
through error to consider . a submission [under s.26(2) in NSW or
s.88(2) in Queensland], is not a matter which the legislature
intended would invalidate the decision”.
[t]he rejection by the NSW Court of Appeal “as a false
premise the proposition that the scope of the payment schedule and
the identification of submissions “duly made” . were
matters to be objectively determined by the Court”.
John Holland is also cited with
approval in Annie Street JV Pty Ltd v MCC Pty Ltd &
Sons [2016] QSC 268 per Flanagan J at [72].
In Civmec Electrical and Instrumental Pty Ltd v
Southern Cross Electrical Engineering Limited [2019] QSC
300 at [31] – [38], her Honour Justice Mullins found that an
adjudicator’s decision to treat parts of the adjudication
response as not being properly made (even if in error) is a
decision within jurisdiction and not reviewable.
In Wiggins Island Coal Export Terminal Pty Ltd v
Monadelphous Engineering Pty Ltd & Ors [2016] QSC 96
at [12], [57] – [84], his Honour Justice Philip McMurdo rejected
WICET’s complaints of both jurisdictional error and breach of
natural justice when an adjudicator refused to consider a new delay
report (the “Evans & Peck Report”) on the basis it
contained new EOT periods and went beyond the reasons in the
payment schedule. Justice McMurdo concluded he was unable to find
there was an error, but even if there was one, it was not an error
which affected validity.
Neither of these decisions were included in Acciona, likely because of their lack
of direct relevance to the line of authorities which was
determinative of the dispute therein.
A further example is Thiess Pty Ltd v Civil Works Australia Pty
Ltd [2010] QSC 187 where there was no jurisdictional error
on the part of the adjudicator in failing to consider sections of a
contract which were raised for the first time in the adjudication
response but not the payment schedule.
The Court determined that s 26(2)(b) of the Act (s 88(2) of BIFA (Qld)) did not provide a
positive obligation on the adjudicator to consider arguments
relating to sections of the contract which were new and independent
assertions made for the first time only in the adjudication
response.
Denial of Natural Justice
Jurisdictional error will be established if the necessary level
of procedural fairness has not been accorded to a party.
In John Holland Pty Ltd v TAC Pacific Pty Ltd
[2009] QSC 205 at [66] (John Holland)
referred to by White JA with approval in Northbuild Construction P/L v Central Interior
Linings P/L & Ors [2011] QCA 22 at [92], the Court
said:
Adjudicators are not required, and “cannot possibly, in
the time available . give the type of care and attention to the
dispute capable of being provided upon a full curial
hearing”
Again, this is in line with the purpose of BIFA, being a quick
resolution to payment claims in what is sometimes referred to as a
“pressure cooker” environment.
However, in certain circumstances, such as where an adjudicator
decides a point on a basis not argued by the parties, the error may
amount to a denial of natural justice, thereby affecting the
validity of the decision.
In order to be successful, the applicant must show both:
- The denial of natural justice; and
- That it was material or substantial.
For the second “materiality” limb, John Holland at [61] stated that the
question is whether:
The matter about which the adjudicator did not provide an
opportunity to be heard was a point upon which the adjudicator
based his or her decision and was significant to the actual
determination.
It is not that the adjudicator would have changed their
mind, but that they could have changed their mind. The Court
said it is sufficient that there be “something to be put
that might well persuade the adjudicator to change his or her
mind.”: John Holland at [40]; Cragcorp Pty Ltd v Qld Civil Engineering Pty
Ltd & Ors [2018] QSC 203 per Lyons SJA at [89].
So, if there has been a material or substantial denial of
natural justice, together with materiality, then this may establish
a jurisdictional error and allow for the Court to review a BIFA
adjudication decision.
Failure to Determine the Amount of the Payment Claim
In relation to reviewing a BIFA adjudication decision, if an
adjudicator fails to determine an adjudicated amount, then this may
result in a jurisdictional error.
This is distinct from determining the amount which a party
alleges is wrong. The adjudicator must decide an amount which is
due.
Section 88(1)(a) of the BIFA states:
(1) An adjudicator is to decide
(a) the amount of the progress payment, if any, to be paid
by the respondent to the claimant (the “adjudicated
amount“).
By failing to adjudicate an adjudicated amount, an adjudication
decision can be void for jurisdictional error.
In Parrwood Pty Ltd v Trinity Constructions
(Aust) Pty Ltd [2020] NSWCA 172 the adjudicator
adjudicated the amount of the adjudication to be
“no amount” (instead of
say, $nil or $0.00).
The Court of Appeal said at [27]:
The mere fact that his reasons disclose error of law does
not vitiate the determination. However, this error of law led to
the adjudicator not doing the very thing he was required by s
22(1)(a) [88(1)(a) in BIFA] to do, namely, determine the amount of
the progress payment to be paid by Parrwood to Trinity. That is as
clear a case as one might find of misconception of function
amounting to jurisdictional error.
So, there must be a determination, even if the determination is
$nil or $0.00, in order to fulfil the statutory function.
Incorrect or Multiple Building Contracts
The payment claim (or claims) must be from the relevant contract
and cannot be from different contracts.
If the adjudicator fails to make a determination about this, or
makes the incorrect determination about the building contract, then
this may allow for review for jurisdictional error.
In Trinco (NSW) Pty Ltd v Alpha A Group Pty
Ltd [2018] NSWSC 239 McDougall J said at [60] to [61]:
Progress claim 3 related to work done under two contracts
(the written subcontract made on 6 March 2017, and the fresh
subcontract made on 8 June 2017). It must follow that the progress
claim could not constitute a valid payment claim . It must follow,
in turn that progress claim 3 could not be the foundation of a
valid adjudication application.
In Matrix Projects (Qld) Pty Ltd v Luscombe
[2013] QSC 4, Douglas J said at [20]:
Accordingly, the payment claim made cannot be described as
one being made under a single construction contract whether the
relationship be described more generally as an arrangement or not.
Therefore, the variety of different types of contract for
construction work relied upon in the payment claim is fatal to its
validity.
In Acciona Infrastructure Australia Pty Ltd v
Holcim (Australia) Pty Ltd [2020] NSWSC 1330 at [40] -
[42], Hammerschlag J decided that the Adjudication Determination
2020061EA made by the second defendant was void and quashed on the
basis that the relevant payment claim was subject to more than one
(1) contract:
The Adjudicator had no jurisdiction because the Payment
Claim was invalid and ineffective to engage the operation of the
Act. By the parties’ express agreement in cl 2 of the
Agreed Terms, each time a purchase order was issued, a separate
contract came into existence between Acciona and Holcim on the
terms set out in the GSA. Each such contract was governed by terms
contained in the overarching GSA instrument, which terms became
incorporated in every subsequent separate contract, but each time
Acciona placed a purchase order, a separate contract for discrete
work with a separate payment date came into existence
. Applying Trinco, the Payment Claim, which straddled
numerous purchase orders (and therefore numerous contracts) with
separate payment dates, did not constitute a valid payment
claim
. It follows that the Determination is void and will be
quashed.
In S.H.A. Premier Constructions Pty Ltd v Lanskey
Constructions & Ors [2019] QSC 81, it was also
submitted that the works were subject to different contracts.
However, Boddice J found at [48] and [49] that they were not
different contracts, but approved variations, and so the
adjudication decisions were not invalid.
Each matter will be determined on the basis of its own
contractual matrix.
Reasonable Apprehension of Bias
The test for the reasonable apprehension of bias was given in Johnson v Johnson [2000] HCA 48,
where Gleeson CJ, Gaudron, McHugh, Gummow, and Hayne JJ of the High
Court said:
Whether a fair-minded lay observer might reasonably
apprehend that the judge might not bring an impartial and
unprejudiced mind to the resolution of the question the Judge is
required to decide.
In Reiby Street v Winterton [2005] NSWSC
545 the Court there was apprehended bias and that determination
of the adjudicator was void because of a previous dispute between
the adjudicator and the plaintiff. Master Macready said at
[56]-[58]:
56 In the circumstances of the present case, proceeding with
the hearing was not a waiver such that Mr Hutchinson can not in the
appeal, or the summons, raise the reasonable apprehension.
57 It necessarily follows that in the present circumstances
the plaintiff has not waived his right to object by continuing to
participate in the adjudication and not immediately commencing
proceedings in this Court.
58 In these circumstances there is no waiver and no reason
to refuse to set aside the determination on the ground of a breach
of natural justice. I will make a declaration in terms of paragraph
1 of the Summons and I will hear the parties on any other
orders.
In Allpro Building Services Pty Ltd v Micos
Architectural Division Pty Ltd [2010] NSWSC 474 the Court
decided an adjudicator’s determination was void due to the
appearance of bias arising from the adjudicator being in a dispute
with the plaintiff over fees from another adjudication. Einstein J
said at [16]:
There is absolutely no doubt from the materials to which I
have referred that the adjudicator breached the rules of natural
justice in terms of the tests already referred to. The views of a
fair-minded bystander as to the adjudicator’s conduct would
clearly give rise to the fact that that conduct exhibited a
reasonable apprehension of bias.
So, whilst very rare, a reasonable apprehension of bias may also
provide grounds for declaring an adjudication decision void.
Fraud
The Courts have found that fraud can be a sufficient reason to
raise jurisdictional error.
Where the adjudicator is complicit in the fraud, the
adjudication decision can be void.
Where the adjudicator is not complicit in the fraud, the
adjudication can be voidable and can be set aside.
This is perhaps the rarest of the jurisdictional errors.
In Brodyn Pty Ltd (t/as Time Cost & Quality)
v Davenport (2004) 61 NSWLR 421 Hodgson JA found, with
Mason P and Giles JA agreeing:
If there is fraud of the claimant in which the adjudicator
is also involved, the determination will be void because the
adjudicator has not bona fide attempted to exercise the power. If
the determination is induced by fraud of the claimant in which the
adjudicator is not involved, then I am inclined to think that the
determination is not void but voidable; and it is liable to be set
aside by proceedings of the kind appropriate to judgments obtained
by fraud.
In Hansen Yuncken Pty Ltd v. Ian James Ericson
trading as Flea’s Concreting [2010] QSC 156, the
subcontractor provided documents to the adjudicator which were
falsified, and therefore fraudulent. These documents had not been
provided at the same time to the contractor. McMurdo J said at
[14]:
In my conclusion . the reason is that there [is] a
jurisdiction to defeat what would otherwise be the effect of an
adjudicator’s decision procured by the fraud of the claimant,
quite apart from the prerogative remedies. That jurisdiction was
recognised by Hodgson JA in Brodyn .
In QC Communications NSW Pty Ltd v CivComm Pty
Ltd [2016] NSWSC 1095, the adjudication determination in
favour of the defendant was set aside for fraud. Ball J followed
the precedent discussed above at [31], [33] and [36]:
The general principle in respect of a determination obtained
by fraud was stated by Hodgson JA in Brodyn Pty Ltd v
Davenport [2004] NSWCA 394 at [60] in these terms:
If the determination is induced by fraud of the claimant in
which the adjudicator is not involved, then I am inclined to think
that the determination is not void but voidable; and it is liable
to be set aside by proceedings of the kind appropriate to judgments
obtained by fraud.
That view was accepted by the Queensland Supreme Court
in Hansen Yuncken Pty Limited v Ericson [2011] QSC
327.
I am satisfied that the determination was induced by fraud
in this case. That fraud consisted of CivComm relying on invoices
in support of its claim that it, and that Mr Zakaria in particular,
knew were false because they included claims for work that CivComm
knew had not been performed
. In my opinion, the fraud was sufficiently significant and
widespread that it had a substantial effect on the
Adjudicator’s determination. As a result, the determination
should be set aside.
If the claimant or respondent have submitted documents which are
falsified, which would have a substantial effect of the
adjudicator’s decision, then this may be jurisdictional error,
allowing a party to apply for judicial review.
Quantum Meruit Claims
An adjudicator must confine the adjudication to the items
prescribed at section 88 of the BIFA.
In Unifor Australia Pty Ltd v Katrd Pty Ltd atf
Morshan Unit Trust t/as Beyond Completion Projects [2012] QSC
252, the adjudicator decided the amount of the claim by
reference to irrelevant or unrelated considerations not prescribed
by section 88. Daubney J decided at [35]:
It follows that I conclude that the adjudicator fell into
jurisdictional error by doing something which he lacked authority
to do. The adjudicator did not have the power to make an assessment
on a quantum merit; his power to assess the amount of the payment
claim was prescribed by s 26 [now section 88] . The
adjudicator’s decision, in this case was unlawful, and
therefore void.
The adjudicator must adhere strictly to the prescribed process
at section 88 of the BIFA. This involves consideration of the
contract, and as quantum meruit claims are extra-contractual
assessments based on reasonableness, they are outside the
legislative regime.
Awarding More Than the Payment Claim
An adjudicator does not have the jurisdiction to award an amount
greater than what was claimed in the payment claim.
In Creative Building Services Pty Ltd v TIO Air
Conditioning Pty Ltd [2016] ACTSC 367, the claimant
claimed $41,710.67 for the payment claim. However, the adjudicator
determined that the plaintiff was liable to pay an amount of
$143,293.27. Mossop AsJ said at [50]:
While it might be possible to characterise the existence of
a payment claim for a claimed amount at least as great as the
amount awarded as a jurisdictional fact necessary for the making of
an award, I consider that it is more appropriate to characterise
what occurred in the present case as a jurisdictional error. The
jurisdictional error involved the adjudicator exceeding the
jurisdiction which he was given as a consequence of TIO’s
payment claim.
In Fulton Hogan Construction Pty Ltd v QH & M
Birt Pty Ltd [2019] QSC 23, the Court decided the
adjudicator was in error where the adjudicator had not valued work
in accordance with the contract.
Adjudicator not Giving Reasons for the Decision
An adjudicator must give reasons for the decision.
Section 88(5) of the BIFA says:
(5) The adjudicator’s decision must:
(a) be in writing; and
(b) include the reasons for the decision, unless the
claimant and the respondent have both asked the adjudicator not to
include the reasons in the decision.
In Sierra Property Qld Pty Ltd v National
Construction Management Pty Ltd [2016] QSC 108, Jackson J
held at [67]:
The failure to include reasons for the decision amounts to a
jurisdictional error.
In Annie Street JV Pty Ltd v MCC Pty Ltd
[2016] QSC 268, Flanagan J said, at [23]:
Given the mandatory language of s 26(3)(b) [now 88(5) of
BIFA], absent the consent of both parties for the adjudicator not
to include reasons in the decision, it may be accepted that a
complete failure on the part of an adjudicator to give reasons
constitutes jurisdictional error.
So, the adjudication decision must be accompanied by adequate
written reasons. This is not a low bar, and successful challenges
on this basis are rare.
What are Non-Jurisdiction Errors in Adjudication
Applications?
When thinking about reviewing a BIFA adjudication decision,
non-jurisdictional errors are errors which are not jurisdictional
in nature, and therefore do not allow for review of the
adjudicator’s decision. Non-jurisdictional errors can
include:
- Non-jurisdictional error of law;
- Failure to interpret the contract correctly; and/or
- Getting the facts of the case wrong.
We will explain these in more detail below.
Non-Jurisdictional Error of Law
An error of law on the face of the record does not automatically
allow for the adjudication decision to be challenged, if it was a
decision within the adjudicator’s jurisdiction to make.
In Shade Systems Pty Ltd v Probuild Constructions
(Aust) Pty Ltd (No 2) [2016] NSWCA 379 the full court of
the New South Wales Court of Appeal reviewed a decision from the
Supreme Court alleging both a denial of procedural fairness and
errors of law. The primary judge rejected the claim of procedural
unfairness but stated that the Court could review
non-jurisdictional errors of law. The appellant appealed to the
Court of Appeal, asserting that there was no power to decide
non-jurisdictional errors of law.
Allowing the appeal, the Court held that the NSW BIFA did not
allow the review of the decision of an adjudicator for anything but
jurisdictional error. The Court held at [73]:
The independent consideration of the Security of Payment Act
set out above supports the conclusion that review is not available
for non-jurisdictional error of law on the face of the
record.
This was followed in EQ Constructions Pty Ltd v A-Civil Aust Pty
Ltd [2021] NSWSC 1604 at [58] where Williams J said:
. [t]he [Act] impliedly excluded certiorari for
non-jurisdictional error of law on the face of the record of an
adjudication determination under that Act . The Full Court held
that the adjudicator’s decision was wrong because he had
misconstrued s 12, but that this was not a jurisdictional
error.
A similar approach has been adopted in Queensland, for example
in Civmec Electrical and Instrumental Pty Ltd v
Southern Cross Electrical Engineering Limited [2019] QSC
300 Mullins J said at [66]:
. [t]he adjudicator’s decision to treat parts of the
adjudication response as new reasons not covered by the payment
schedule (even if in error) was a decision within jurisdiction and
not reviewable.
Failure to Interpret the Contract Correctly
When reviewing a BIFA adjudication decision, an error in the
identification or interpretation of a term of the contract will not
automatically be jurisdictional error allowing a party to challenge
the adjudicator’s decision, unless it pertains to a
jurisdictional threshold issue such as the existence of a
construction contract.
In John Holland Pty Ltd v TAC Pacific Pty Ltd
& Ors [2009] QSC 205 Applegarth J said at [57]:
The statutory scheme may permit an adjudicator to make
unreviewable errors of law in quickly deciding complex legal issues
in adjudications of the present kind after considering the
parties’ submissions.
In Northbuild Construction Sunshine Coast Pty Ltd
v Beyfield Pty Ltd [2014] QSC 80 when discussing the
misinterpretation of a term (or terms) of a construction contract
by the adjudicator, Philip McMurdo J said at [34]:
Therefore I am not persuaded that his error was a
jurisdictional error. But rather it was an error in the
interpretation of the contract which was a task within his
jurisdiction.
Northbuild (above) is supported by Caltex Refineries (Qld) Pty Ltd v Allstate
Access (Aust) Pty Ltd [2014] QSC 223 where Philip McMurdo
J held that misinterpretation of a term (or terms) of the
construction contract is not jurisdictional error. His Honour said
at [36]:
An adjudicator must identify the terms of the relevant
contract and interpret them. Therefore, ordinarily an error in the
interpretation of a contract is not a jurisdictional error for
which an adjudicator’s decisions can be challenged.
This is in line with the overall principles of BIFA and other
security for payment legislation in different Australian states and
territories.
Getting the Facts or Law Wrong
Similarly, if the adjudication decision is decided in error but
was an error within the jurisdiction of the adjudicator, it is not
automatically reviewable.
Quasar Constructions v Demtech Pty Ltd
[2004] NSWSC 116, Barrett J says at [13]:
The plaintiff says, and I agree, that an adjudicator has
jurisdiction only to determine an amount that is, on the basis of
the particular payment claim and payment schedule, a “progress
payment” within the meaning of the Act; and that, in
exercising that jurisdiction, the adjudicator may proceed only in
accordance with the method the Act prescribes for determining the
amount of a “progress payment” in the context of the
particular payment claim and payment schedule. Jurisdictional error
arises if an adjudicator is seen to have embarked on some course
that is foreign or irrelevant to this statutory task.
Jurisdictional error does not arise if, having embarked on the
right course, an adjudicator comes to a wrong conclusion.
A similar conclusion was reached in WA, in WQUBE Port of Dampier -v- Philip Loots of
Kahlia Nominees Ltd [2014] WASC 331 Chaney J said at
[27]:
In my view, that regime supports the conclusion that the
legislature intended to confer upon an adjudicator jurisdiction to
determine questions of law authoritatively, and also the power to
determine those questions wrongly without attracting prerogative
relief.
Therefore, when reviewing a BIFA adjudication decision, errors
of fact or the effect of law which do not go to jurisdiction are
unlikely to be sound bases for challenging enforceability.
What are the Consequences of Jurisdictional Error
The Court has options including:
- declaring all or part of the adjudication decision void;
- remitting it back to an adjudicator; and/or
- seeking further recourse from the Courts.
We will explain these in more detail below.
Declaring all or part of an Adjudication Decision Void
If a Supreme Court judge is convinced that an adjudicator’s
decision is unenforceable, the most common outcome is a declaration
that the decision is void. Any payments made in accordance with the
decision must be returned.
In a review of an adjudication decision, the Queensland Supreme
Court is now able to sever the portion of the decision affected by
jurisdictional error.
This statutory change, introduced in s.101(4) of BIFA in 2017
overturned the common law, and stops the entire adjudication
decision from being void if only one part of it is properly
impugned, and that part may be severed.
The case law leading to that amendment is interesting. In BM Alliance Coal Operations Pty Ltd v BGC
Contracting Pty Ltd [2013] QCA 394 Holmes and Muir JJA and
Ann Lyons J of the Queensland Court of Appeal overturned the
earlier decision of Applegarth J in BM Alliance Coal Operations Pty Ltd v BGC
Contracting Pty (No 2) [2013] QSC 67.
In the first case, Applegarth J decided that parts of the
adjudication decision not affected by jurisdictional error should
be allowed, and the parts of the adjudication affected by
jurisdictional error should be denied.
In the appeal the original decision was set aside because the
Court found at [71] that:
. [o]nce a court determines that a decision of the type in
question is affected by jurisdictional error, the decision cannot
give rise to legal consequences.
The Court then concluded at [77]:
His Honour . erred in finding in his 22 March 2013 reasons
that the adjudication decision, which he held to be affected by
jurisdictional error, retained effect until he exercised his
discretion to grant a declaration or make an order quashing or
setting aside the decision . For the above reasons, the primary
judge’s orders of 22 March 2013 should be set aside.
These were the findings of Muir JA, with Holmes JA and Lyons J
agreeing.
This appeal decision was followed in J Hutchinson Pty Ltd v Cada Formwork Pty Ltd
& Ors [2014] QSC 63 at [81] where Lyons J said:
That conclusion is confirmed by the decision of the Court of
Appeal in BM Alliance Coal Operations Pty Ltd v BGC Contracting Pty
Ltd. In that case, the primary judge had found jurisdictional
error, but refused relief. Muir JA (with whom the other members of
the court agreed) referred to decisions of the High Court where it
was held that a decision involving jurisdictional error is properly
regarded, in law, as no decision at all. His Honour then held that
declaratory relief was a “remedy dictated by the finding of
jurisdictional error”. He also held that the primary judge
erred in law in withholding such relief.
Following these decisions, s.101(4) was introduced,
providing:
If, in any proceedings before a court in relation to any
matter arising under a construction contract, the court finds that
only a part of an adjudicator’s decision under this chapter is
affected by jurisdictional error, the court may-
(a) identify the part affected by the error; and
(b) allow the part of the decision not affected by the error
to remain binding on the parties to the proceeding.
Therefore, in Queensland, severance is legislatively permitted.
The position in other States and Territories will be determined by
their own legislation.
So, once the adjudication is declared void and set aside, then
what?
Remitting it Back to an Adjudicator
In some cases, when reviewing a BIFA adjudication decision, a
Court can remit the decision back to the adjudicator for further
determination.
This is discretionary, and a number of factors must be
considered. However, the essential considerations appear to be:
- where the adjudicator lacked jurisdiction, the matter should
not be remitted back to the adjudicator; and - where there is a jurisdictional error, the matter can be
remitted back to the adjudicator.
It is not a common outcome. Indeed, Heavy Plant Leasing Pty Ltd v McConnell Dowell
Constructors (Aust) Pty Ltd [2013] QCA 386 identifies a
number of problems with remitting back to the adjudicator.
Ultimately, considering all of the discretionary factors (or
lack thereof), the Court of Appeal refused to exercise its
discretion to remit, Muir JA said at [67], with Gotterson JA &
Morrison JA agreeing:
In the absence of more comprehensive argument on this
Court’s power to remit an adjudication to an adjudicator in the
circumstances under consideration, I prefer to base my decision on
discretionary grounds. In my view, the following matters tell
against the remittal sought by the appellant. The provision of such
a remedy would be contrary to the quick, cheap and simple processes
envisaged by the Act. Moreover, as Macfarlan JA pointed out in
Cardinal Project Services Pty Ltd v Hanave Pty Ltd, by the time the
adjudicator decided the matter after remittal, circumstances may
have changed significantly from the time when the adjudicator was
considering his original determination. The payment schedule may be
outdated. Other defects may have come to light. The removal of
adjudicator’s decisions under the Act from the scope of
Judicial Review is a further indication of a legislative desire
that the Act’s mechanisms be quick, cheap and simple. Also any
remittal order would necessarily require the adjudicator to make a
decision outside the time permitted by s 25(3) unless the parties
agreed to an extension of time.
The Adjudication Review Procedure
The procedure for reviewing an adjudication decision is to file
an originating application in the Supreme Court of Queensland.
The originating application may require the following
orders:
- an undertaking as to damages;
- payment of the adjudicated amount into Court;
- the parties being restrained from enforcing the adjudication
decision or adjudication certificate pending final
determination; - the dates on which the parties have to file written
submissions; and - a date for the hearing by a Supreme Court judge.
This would be supported by an affidavit in support of the application.
It is very important that you seek advice and assistance
with prosecuting or defending reviewing a BIFA adjudication
decision, contact our construction lawyers today. We work closely
with specialist counsel to obtain the best outcomes for our
clients.
CONTACT A CONSTRUCTION LAWYER TODAY
OR CALL: 1300 545 133 FOR A FREE PHONE
CONSULTATION
The content of this article is intended to provide a general
guide to the subject matter. Specialist advice should be sought
about your specific circumstances.